Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 91: In a project, total float measures the:

A. Ability to shuffle schedule activities to lessen the duration of the project.
B. Amount of time an activity can be extended or delayed without altering the project finish date.
C. Cost expended to restore order to the project schedule after crashing the schedule.
D. Estimate of the total resources needed for the project after performing a forward pass.

Question 92: Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A. Historical relationships
B. Dependency determination
C. Bottom-up estimating
D. Rolling wave planning

Question 93: Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A. Perform Quality Assurance
B. Direct and Manage Project Work
C. Monitor and Control Project Work
D. Perform Integrated Change Control

Question 94: Which tool or technique is used in the Estimate Costs process?

A. Acquisition
B. Earned value management
C. Vendor bid analysis
D. Forecasting

Question 95: Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A. Supportive
B. Directive
C. Controlling
D. Instructive

Question 96: An input to the Identify Stakeholders process is:

A. The project management plan.
B. The stakeholder register.
C. Procurement documents.
D. Stakeholder analysis.

Question 97: Identify Risks is part of which Process Group?

A. Planning
B. Executing
C. Closing
D. Initiating

Question 98: Which tool or technique is used in the Perform Integrated Change Control process?

A. Decomposition
B. Modeling techniques
C. Resource optimization
D. Meetings

Question 99: A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A. Start-to-start (SS).
B. Start-to-finish (SF).
C. Finish-to-start (FS).
D. Finish-to-finish (FF).

Question 100: What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A. $50
B. $100
C. $125
D. $175